# 卡拉帕蒂纳矿

**卡拉帕蒂纳矿**（Carrapateena mine）是南澳大利亚高勒克拉通的一座地下铜、金、银矿，位于阿德莱德西北472公里、奥古斯塔港以北约160公里处，由必和必拓（BHP）在科卡塔人（Kokatha）的传统土地上运营。<sup>[1](https://www.bhp.com/what-we-do/global-locations/australia/south-australia/carrapateena)</sup><sup> • </sup><sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup><sup> • </sup><sup>[3](https://ausenco.com/projects/the-worlds-most-recent-greenfield-copper-mine/)</sup> 该矿产出的铜精矿含金和银，该矿是过去十年间南澳大利亚开发的规模最大的矿业项目之一。<sup>[1](https://www.bhp.com/what-we-do/global-locations/australia/south-australia/carrapateena)</sup><sup> • </sup><sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup>

| 关键事实 | 详情 |
|---|---|
| 矿床类型 | 氧化铁铜金（IOCG）矿床，赋存于角砾化花岗岩杂岩体中，矿物以黄铜矿为主，中心有高品位斑铜矿带<sup>[4](https://www.energymining.sa.gov.au/industry/minerals-and-mining/mining/major-projects-and-mining-activities/major-operating-and-approved-mines/carrapateena)</sup> |
| 位置 | 阿德莱德西北472公里、奥古斯塔港以北约160公里，高勒克拉通东缘<sup>[1](https://www.bhp.com/what-we-do/global-locations/australia/south-australia/carrapateena)</sup><sup> • </sup><sup>[3](https://ausenco.com/projects/the-worlds-most-recent-greenfield-copper-mine/)</sup> |
| 时间线 | 2005年发现；2016年11月开工建设；2019年12月产出首批精矿；2023年随OZ Minerals收购并入必和必拓<sup>[5](https://www.mdpi.com/2075-163X/15/10/1018)</sup><sup> • </sup><sup>[6](https://www.abc.net.au/news/2016-11-03/carrapateena-mine-construction-officially-launched-in-sa/7993158)</sup><sup> • </sup><sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup> |
| 采矿方法 | 地下分段崩落法，并在其下方为下部矿体开发块体崩落采区<sup>[7](https://papers.acg.uwa.edu.au/p/2205_19_Zhang/)</sup> |
| 处理能力 | 2020年达产时铭牌产能为425万吨/年，2026年经HydroFloat粗颗粒浮选项目提升至700万吨/年；块体崩落扩建目标为最高1200万吨/年<sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup><sup> • </sup><sup>[8](https://energymining.sa.gov.au/home/events/premiers-awards-energy-and-mining/2025-premiers-awards-in-energy-and-mining-winners/award-winners/productivity-improvement/bhp-resources-award-winner)</sup><sup> • </sup><sup>[9](https://www.tradingview.com/news/reuters.com%2C2026-08-18%3Anewsml_RSR0375Ra%3A0-reg-bhp-group-limited-bhp-fy2026-results-announcement/)</sup> |
| 资源量 | 9亿吨，品位0.56%铜、0.24克/吨金、3克/吨银（探明+控制+推断，截至2023年6月23日）<sup>[5](https://www.mdpi.com/2075-163X/15/10/1018)</sup> |
| 矿权 | 采矿租约ML 6471及五项杂项用途许可证，六个矿权地合计约44,144公顷，多数于2039年1月到期<sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup> |

## 矿床地质

卡拉帕蒂纳是高勒克拉通东缘的一座氧化铁铜金（IOCG）矿床，位于奥林匹克铜金成矿省内，该成矿省还赋存有奥林匹克坝和普洛米嫩特山。<sup>[5](https://www.mdpi.com/2075-163X/15/10/1018)</sup><sup> • </sup><sup>[10](https://digital.library.adelaide.edu.au/items/45bed316-e202-4a5c-899d-328d443806c4)</sup> 南澳大利亚地质调查局将其描述为赋存于角砾化花岗岩杂岩体中的IOCG矿床，矿物以黄铜矿为主，中心有高品位斑铜矿带。<sup>[4](https://www.energymining.sa.gov.au/industry/minerals-and-mining/mining/major-projects-and-mining-activities/major-operating-and-approved-mines/carrapateena)</sup> 与奥林匹克坝一样，它呈现出矿物分带：内部为高品位斑铜矿±辉铜矿带，外围为黄铜矿-斑铜矿带，最外层为黄铁矿-黄铜矿带。<sup>[5](https://www.mdpi.com/2075-163X/15/10/1018)</sup>

**容矿岩石与年龄。** 矿床赋存于古元古代多宁顿组（Donington Suite）强烈角砾化的花岗质岩石中，年龄为1857±6 Ma，位于约470米厚的平缓新元古代覆盖沉积层之下。<sup>[11](https://minerals.sarig.sa.gov.au/MineralDepositDetails.aspx?DEPOSIT_NO=8303)</sup> 通过磷灰石、赤铁矿和磷钇矿的铀-铅年代学测定，矿化年龄约为1585 Ma，与约1595–1570 Ma的希尔塔巴组（Hiltaba Suite）和高勒山脉火山岩岩浆事件同期，该事件是高勒克拉通主要IOCG矿床背后的热系统。<sup>[5](https://www.mdpi.com/2075-163X/15/10/1018)</sup><sup> • </sup><sup>[12](https://energymining.sa.gov.au/industry/geological-survey/mesa-journal/previous-feature-articles/investigating_the_spectrum_of_mineral_deposits_in_the_gawler_craton)</sup> 赤铁矿是铁交代作用的产物，为主要脉石矿物，矿石中稀土元素和铀的地球化学浓度异常，这是IOCG系统的典型特征。<sup>[5](https://www.mdpi.com/2075-163X/15/10/1018)</sup>

截至2023年6月23日，探明、控制和推断类别的矿石资源总量为9亿吨，品位0.56%铜、0.24克/吨金、3克/吨银。<sup>[5](https://www.mdpi.com/2075-163X/15/10/1018)</sup>

## 发现与开发

该矿床于2005年发现。<sup>[5](https://www.mdpi.com/2075-163X/15/10/1018)</sup> 2011年，科卡塔乌万卡拉原住民地权申请人与OZ Minerals子公司达成协议，允许在托伦斯湖附近继续勘探，条件是保护原住民地权权益。<sup>[13](https://www.abc.net.au/news/2011-08-17/mining-agreement/2843368)</sup> OZ Minerals于2016年2月加速项目研究，旨在大宗商品周期低点进行建设；2016年11月，南澳大利亚州州长杰伊·韦瑟里尔（Jay Weatherill）在预计将创造1000多个地区就业岗位的现场正式启动建设。<sup>[14](https://www.abc.net.au/news/2016-02-26/oz-minerals-touts-jobs-in-cautious-carrapateena-announcement/7202502)</sup><sup> • </sup><sup>[6](https://www.abc.net.au/news/2016-11-03/carrapateena-mine-construction-officially-launched-in-sa/7993158)</sup> 当时，通往地下约500米深处铜矿床的5.5公里隧道已在施工中。<sup>[6](https://www.abc.net.au/news/2016-11-03/carrapateena-mine-construction-officially-launched-in-sa/7993158)</sup>

**选矿厂建设。** 奥森科（Ausenco）以固定价格EPC合同在20个月建设期内（2018年第二季度至2020年第一季度）交付了450万吨/年的铜选矿厂。<sup>[3](https://ausenco.com/projects/the-worlds-most-recent-greenfield-copper-mine/)</sup> 首批精矿于2019年12月产出，选矿厂在调试完成后一个月内达到铭牌处理能力。<sup>[3](https://ausenco.com/projects/the-worlds-most-recent-greenfield-copper-mine/)</sup> 优化设计在整个选矿厂寿命期内用电量减少30%，占地面积比可行性研究设计小50%。<sup>[3](https://ausenco.com/projects/the-worlds-most-recent-greenfield-copper-mine/)</sup> 奥森科还交付了非工艺基础设施，包括距现场11公里的尾矿储存设施管线、一座配有六台泵的单泵站、由50公里管道供水的水井场以及一座饮用水厂。<sup>[3](https://ausenco.com/projects/the-worlds-most-recent-greenfield-copper-mine/)</sup> 施工队伍采用飞进飞出模式，30%为南澳大利亚本地工人，11%的劳动力来自奥古斯塔港社区，通过与原住民科卡塔人合作开展的就业项目实现。<sup>[3](https://ausenco.com/projects/the-worlds-most-recent-greenfield-copper-mine/)</sup>

## 采矿方法：从分段崩落到块体崩落

卡拉帕蒂纳采用分段崩落法（SLC）开采，即在连续的各分段中爆破矿石并从下方放出。<sup>[7](https://papers.acg.uwa.edu.au/p/2205_19_Zhang/)</sup> 地下作业于2020年爬坡至425万吨/年，2022年崩落体扩展至地表。<sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup>

**块体崩落扩建。** 为最大化铜金矿体下部深部部分的价值，OZ Minerals及随后的必和必拓研究了向块体崩落法的过渡。块体崩落法是一种高处理能力方法，通过大规模拉底使矿体在自重下崩塌破碎，矿石依靠重力进入单一出矿水平的放矿漏斗。<sup>[7](https://papers.acg.uwa.edu.au/p/2205_19_Zhang/)</sup><sup> • </sup><sup>[15](https://informs-sim.org/wsc20papers/053.pdf)</sup> 截至2022年已完成的可行性研究涵盖崩落区范围确定、矿山布局、产能爬坡、物料搬运系统选择、通风与排水，以及上方运营中的分段崩落与下方建设的块体崩落之间的相互作用。<sup>[7](https://papers.acg.uwa.edu.au/p/2205_19_Zhang/)</sup> 矿体近垂直的排列使“上部分段崩落、下部块体崩落”的组合布置成为可能；这缩短了分段崩落的开拓准备时间，同时在块体崩落建成后降低了运营成本。<sup>[15](https://informs-sim.org/wsc20papers/053.pdf)</sup> 到2026财年，通往块体崩落底部的斜坡道已完工，地下基础设施建设计划于2027财年上半年开始，块体崩落爬坡计划于2030财年启动，将处理能力提升至1200万吨/年。<sup>[9](https://www.tradingview.com/news/reuters.com%2C2026-08-18%3Anewsml_RSR0375Ra%3A0-reg-bhp-group-limited-bhp-fy2026-results-announcement/)</sup> 必和必拓将块体崩落定位为实现可持续开采数代人、现金成本处于最低四分位的矿山运营的手段。<sup>[16](https://www.bhp.com/-/media/Documents/Investors/Annual-Reports/2024/240827_bhpannualreport2024)</sup>

由于矿体上方存在大量较弱的覆盖层序，预测细粒物料通过崩落体的流动对储量估算至关重要；卡拉帕蒂纳的监测结合品位测量、标记安装和现场观察来校准流动模型，包括距放矿点100米以上的远场流动。<sup>[17](https://papers.acg.uwa.edu.au/p/2063_33_Hocking/)</sup>

## 选矿与HydroFloat项目

矿石在现场经破碎、磨矿和泡沫浮选分离，硫化铜精矿销往全球精矿市场。<sup>[5](https://www.mdpi.com/2075-163X/15/10/1018)</sup> 2024年，矿山投运了2号破碎站；2025年投运了HydroFloat项目，这是一套粗颗粒浮选装置，可回收原本会损失到尾矿中的粗颗粒。<sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup><sup> • </sup><sup>[8](https://energymining.sa.gov.au/home/events/premiers-awards-energy-and-mining/2025-premiers-awards-in-energy-and-mining-winners/award-winners/productivity-improvement/bhp-resources-award-winner)</sup> 耗资1.6亿澳元的HydroFloat项目使该矿成为全球少数以这一规模采用此技术的铜矿之一；该项目与其他消除瓶颈项目一起，将处理能力从425万吨/年的铭牌产能提升至700万吨/年，同时保持甚至提高了矿物回收率；700万吨/年的爬坡于2026年实现。<sup>[18](https://www.linkedin.com/posts/joe-seppelt-24675855_were-proud-to-announce-the-successful-commissioning-activity-7371088223457976320-Vmt_)</sup><sup> • </sup><sup>[8](https://energymining.sa.gov.au/home/events/premiers-awards-energy-and-mining/2025-premiers-awards-in-energy-and-mining-winners/award-winners/productivity-improvement/bhp-resources-award-winner)</sup><sup> • </sup><sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup> 该项目在2025年南澳大利亚州长能源与矿业奖中获得生产力提升类别奖项。<sup>[8](https://energymining.sa.gov.au/home/events/premiers-awards-energy-and-mining/2025-premiers-awards-in-energy-and-mining-winners/award-winners/productivity-improvement/bhp-resources-award-winner)</sup>

## 所有权、矿权与基础设施

必和必拓自2023年收购OZ Minerals以来持有100%所有权。<sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup> 该项目持有采矿租约ML 6471及杂项用途许可证MPL 149、152、153、154和156，由南澳大利亚州政府授予，除MPL 149于2038年7月到期外，其余均于2039年1月到期；矿权地合计约44,144公顷。<sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup> 九项采掘矿物租约EML 6480至6488于2018年7月授予，用于辅助用途。<sup>[4](https://www.energymining.sa.gov.au/industry/minerals-and-mining/mining/major-projects-and-mining-activities/major-operating-and-approved-mines/carrapateena)</sup> 进场道路为60公里私家道路，铜精矿通过公路和铁路运输。<sup>[2](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)</sup>

**电力与水。** 该矿位于必和必拓南澳铜业板块内，该板块还包括奥林匹克坝和普洛米嫩特山；根据2025年基荷安排，Neoen公司的盖德北风电场和盖德电池储能向该板块供应100兆瓦可再生电力，预计到2030财年可用可再生能源满足南澳铜业约70%的电力需求。<sup>[19](https://www.bhp.com/news/media-centre/releases/2025/09/bhp-powers-ahead-with-third-renewable-electricity-deal-for-copper-sa)</sup> 拟建的北方供水项目是在怀阿拉附近穆拉夸纳建设一座年产510亿升的海水淡化厂，包括一条约46公里的侧支管道，终点为卡拉帕蒂纳矿的交付点。<sup>[20](https://plan.sa.gov.au/development_applications/state_development/impact-assessed-development/majors/major_projects/majors/northern-water-mullaquana)</sup>

## 产量记录

2025财年，卡拉帕蒂纳通过分段崩落法实现了更高的生产率，铜年产量强劲，黄金产量创纪录。<sup>[21](https://www.tradingview.com/news/reuters.com%2C2025-07-18%3Anewsml_RSR5922Ra%3A0-reg-bhp-group-limited-quarterly-activities-report/)</sup> 截至2026财年的三年间，南澳铜业板块整体铜产量约为32万吨/年，包括金、银和铀在内的铜当量超过45万吨/年。<sup>[9](https://www.tradingview.com/news/reuters.com%2C2026-08-18%3Anewsml_RSR0375Ra%3A0-reg-bhp-group-limited-bhp-fy2026-results-announcement/)</sup>

## References

1. [Carrapateena, BHP](https://www.bhp.com/what-we-do/global-locations/australia/south-australia/carrapateena)
2. [BHP Form 20-F, Carrapateena property description, U.S. Securities and Exchange Commission](https://www.sec.gov/Archives/edgar/data/811809/000119312526354647/bhp-20260630.htm)
3. [Carrapateena copper mine project, Ausenco](https://ausenco.com/projects/the-worlds-most-recent-greenfield-copper-mine/)
4. [Carrapateena Project, Energy & Mining, Government of South Australia](https://www.energymining.sa.gov.au/industry/minerals-and-mining/mining/major-projects-and-mining-activities/major-operating-and-approved-mines/carrapateena)
5. [Minor and Trace Elements in Copper Tailings (2025), Minerals, MDPI](https://www.mdpi.com/2075-163X/15/10/1018)
6. [Carrapateena Mine construction officially launched in outback South Australia, ABC News (3 November 2016)](https://www.abc.net.au/news/2016-11-03/carrapateena-mine-construction-officially-launched-in-sa/7993158)
7. [Zhang, Q & Hocking, RJ 2022, Carrapateena block cave mine design and planning: feasibility study, Australian Centre for Geomechanics](https://papers.acg.uwa.edu.au/p/2205_19_Zhang/)
8. [BHP's Carrapateena HydroFloat project, 2025 Premier's Awards in Energy and Mining winner](https://energymining.sa.gov.au/home/events/premiers-awards-energy-and-mining/2025-premiers-awards-in-energy-and-mining-winners/award-winners/productivity-improvement/bhp-resources-award-winner)
9. [BHP FY2026 Results Announcement, Reuters via TradingView](https://www.tradingview.com/news/reuters.com%2C2026-08-18%3Anewsml_RSR0375Ra%3A0-reg-bhp-group-limited-bhp-fy2026-results-announcement/)
10. [North, B 2020, The geochemistry of rare earth element-bearing minerals at the Carrapateena deposit, University of Adelaide thesis](https://digital.library.adelaide.edu.au/items/45bed316-e202-4a5c-899d-328d443806c4)
11. [Carrapateena mineral deposit details, SA Geodata Database](https://minerals.sarig.sa.gov.au/MineralDepositDetails.aspx?DEPOSIT_NO=8303)
12. [Investigating the spectrum of mineral deposits in the Gawler Craton, Energy & Mining](https://energymining.sa.gov.au/industry/geological-survey/mesa-journal/previous-feature-articles/investigating_the_spectrum_of_mineral_deposits_in_the_gawler_craton)
13. [Native title claimants reach mining agreement, ABC News (17 August 2011)](https://www.abc.net.au/news/2011-08-17/mining-agreement/2843368)
14. [Oz Minerals flags 400 new jobs in 'cautious' Carrapateena project announcement, ABC News (26 February 2016)](https://www.abc.net.au/news/2016-02-26/oz-minerals-touts-jobs-in-cautious-carrapateena-announcement/7202502)
15. [Eustace, Lagacé & Bobbermen 2020, Simulation capacity analysis for the Carrapateena block cave, Winter Simulation Conference](https://informs-sim.org/wsc20papers/053.pdf)
16. [BHP Annual Report 2024, Copper South Australia](https://www.bhp.com/-/media/Documents/Investors/Annual-Reports/2024/240827_bhpannualreport2024)
17. [Hocking, Fargher & Chester 2020, Marker design and calibration for Carrapateena sub level and block cave, Australian Centre for Geomechanics](https://papers.acg.uwa.edu.au/p/2063_33_Hocking/)
18. [Joe Seppelt, commissioning of the A$160 million HydroFloat at Carrapateena, LinkedIn](https://www.linkedin.com/posts/joe-seppelt-24675855_were-proud-to-announce-the-successful-commissioning-activity-7371088223457976320-Vmt_)
19. [BHP powers ahead with third renewable electricity deal for Copper SA (24 September 2025)](https://www.bhp.com/news/media-centre/releases/2025/09/bhp-powers-ahead-with-third-renewable-electricity-deal-for-copper-sa)
20. [Northern Water – Mullaquana, PlanSA](https://plan.sa.gov.au/development_applications/state_development/impact-assessed-development/majors/major_projects/majors/northern-water-mullaquana)
21. [BHP Quarterly Activities Report, year ended 30 June 2025, Reuters via TradingView](https://www.tradingview.com/news/reuters.com%2C2025-07-18%3Anewsml_RSR5922Ra%3A0-reg-bhp-group-limited-quarterly-activities-report/)

---
*Initially written Oct 15, 2026*

Topic: 物质世界与数学 › 地球科学 › 地质学与矿物学 › Economic and petroleum geology › Copper mines

Copyright 2026 Edgepedia

License: Edgepedia Community License 1.0, https://www.edgepedia.org/edgepedia/license

Source: https://www.edgepedia.org/zh/carrapateena-mine

English original: https://www.edgepedia.org/carrapateena-mine