# 姆潘达恩库瓦项目

姆潘达恩库瓦水电站项目（MNK）是一个规划中的1，500兆瓦径流式水电站大坝，位于[莫桑比克](https://www.edgepedia.org/zh/mozambique)中部太特省赞比西河上，在卡布拉巴萨大坝下游60公里、距太特市60公里处。<sup>[1](https://www.edf.fr/en/the-edf-group/dedicated-sections/journalists/all-press-releases/the-consortium-of-edf-totalenergies-sumitomo-corporation-entered-into-joint-development-agreement-with-the-government-of-mozambique-for-the-1500-mw-mphanda-nkuwa-hydropower-project)</sup> 该项目由[法国电力公司](https://www.edgepedia.org/zh/electricite-de-france)（EDF）、[道达尔能源](https://www.edgepedia.org/zh/totalenergies)和住友商事组成的财团与莫桑比克政府共同开发，旨在扩大国内电力供应并向南部非洲邻国出口电力。<sup>[1](https://www.edf.fr/en/the-edf-group/dedicated-sections/journalists/all-press-releases/the-consortium-of-edf-totalenergies-sumitomo-corporation-entered-into-joint-development-agreement-with-the-government-of-mozambique-for-the-1500-mw-mphanda-nkuwa-hydropower-project)</sup>

| 关键事实 | 详情 |
|---|---|
| 装机容量与类型 | 赞比西河太特省径流式电站，装机1，500兆瓦，位于卡布拉巴萨下游60公里<sup>[1](https://www.edf.fr/en/the-edf-group/dedicated-sections/journalists/all-press-releases/the-consortium-of-edf-totalenergies-sumitomo-corporation-entered-into-joint-development-agreement-with-the-government-of-mozambique-for-the-1500-mw-mphanda-nkuwa-hydropower-project)</sup> |
| 设计 | 长700米、高86米的混凝土重力坝，设13道泄洪闸；4台365兆瓦弗朗西斯水轮机；满负荷年发电量约8，600吉瓦时<sup>[2](https://invest.sadc.int/opportunities/project-details/view_express_entity/32)</sup> |
| 股权结构 | 财团（EDF 40%、道达尔能源30%、住友商事30%）持有70%；国有公司莫桑比克电力公司（EDM）和卡布拉巴萨水电公司（HCB）持有30%<sup>[1](https://www.edf.fr/en/the-edf-group/dedicated-sections/journalists/all-press-releases/the-consortium-of-edf-totalenergies-sumitomo-corporation-entered-into-joint-development-agreement-with-the-government-of-mozambique-for-the-1500-mw-mphanda-nkuwa-hydropower-project)</sup> |
| 造价 | 估算从45亿美元（国际金融公司，2022年）到50至60亿美元（世界银行行长估算），含14亿美元输电线路在内为64亿美元<sup>[3](https://www.ifc.org/en/pressroom/2022/ifc-and-mphanda-nkuwa-implementation-office-sign-agreement-to-support-the-development-of-a-1500-mw-hydropower-project-in-mozambique)</sup><sup> • </sup><sup>[4](https://apnews.com/article/2c661562fb5de1dcaaa5d3681ac86c54)</sup><sup> • </sup><sup>[5](https://www.bhrrc.org/en/latest-news/mozambique-the-mphanda-nkuwa-dam-project-allegedly-poses-severe-human-rights-risks-incl-company-responses/)</sup> |
| 出力分配 | 60%（900兆瓦）承诺用于出口，40%（600兆瓦）预留国内消费<sup>[6](https://ja4change.org/wp-content/uploads/2025/02/jas-summary-of-mnk-concerns_february-2025-1.pdf)</sup> |
| 输电 | 一条650公里、400千伏高压交流线路通往马拉拉的卡塔沙变电站；一条1，300公里、550千伏高压直流线路连接马普托与南非电网<sup>[2](https://invest.sadc.int/opportunities/project-details/view_express_entity/32)</sup> |
| 投运时间 | 据美联社报道为2031年；莫桑比克政府宣布预计2032年商业运营<sup>[4](https://apnews.com/article/2c661562fb5de1dcaaa5d3681ac86c54)</sup><sup> • </sup><sup>[7](https://portaldogoverno.gov.mz/governo-concessiona-empreendimento-hidroelectrico-de-mphanda-nkuwa/)</sup> |

## 技术设计

项目包括大坝、发电站和高压输电基础设施。南部非洲发展共同体投资门户网站描述了一座长700米、高86米的混凝土重力坝，设13道泄洪闸，利用上游卡布拉巴萨水电站释放的水流发电。发电厂房将安装4台365兆瓦的[弗朗西斯水轮机](https://www.edgepedia.org/zh/francis-turbine)，满负荷年发电量约8，600吉瓦时。<sup>[2](https://invest.sadc.int/opportunities/project-details/view_express_entity/32)</sup> 由于采用径流式方案，其小水库蓄水能力有限；2011年为世界自然基金会所做的一项研究指出，水库规模太小，无法支持向下游河段释放环境流量，而大坝本身也不会对卡布拉巴萨的下泄水量构成水文约束。<sup>[8](https://www.researchgate.net/publication/313726306_Implications_of_Mpanda_Nkuwa_Hydropower_Project_for_Environmental_Flow_Releases_in_the_Lower_Zambezi_Valley)</sup>

电力将通过一条650公里长的400千伏高压交流线路送出，连接马拉拉的卡塔沙变电站；另规划一条1，300公里长的550千伏高压直流线路，将马普托变电站与南非电网相连。剩余电力将通过南部非洲电力池协调的电力交易安排出口到邻国。<sup>[2](https://invest.sadc.int/opportunities/project-details/view_express_entity/32)</sup>

## 历史

该大坝最早由当时正在建设卡布拉巴萨的葡萄牙殖民当局提出。莫桑比克独立后，于1996年进行了可行性研究，2002年的一次投资会议吸引了南非、巴西和中国投资者的兴趣。2006年，[中国进出口银行](https://www.edgepedia.org/zh/export-import-bank-of-china)与莫桑比克政府签署了一项23亿美元的谅解备忘录，拟为大坝提供资金，但计划最终落空；2007年莫桑比克取得卡布拉巴萨控制权后，另一次努力同样未能成功。<sup>[9](https://clubofmozambique.com/news/mozambique-mphanda-nkuwa-special-report-by-joseph-hanlon/)</sup>

[菲利佩·纽西](https://www.edgepedia.org/zh/filipe-nyusi)总统于2018年重启该项目，成立了姆潘达恩库瓦水电站项目实施办公室（GMNK），该办公室是矿产资源与能源部下属的专门机构，依据2019年2月7日第18/2019号部长令设立。GMNK受命开发该项目及其配套输电基础设施，并牵头遴选战略合作伙伴。<sup>[9](https://clubofmozambique.com/news/mozambique-mphanda-nkuwa-special-report-by-joseph-hanlon/)</sup><sup> • </sup><sup>[3](https://www.ifc.org/en/pressroom/2022/ifc-and-mphanda-nkuwa-implementation-office-sign-agreement-to-support-the-development-of-a-1500-mw-hydropower-project-in-mozambique)</sup> 2022年5月，国际金融公司与该部宣布合作，为这一1，500兆瓦项目进行项目筹划，包括审查技术设计、环境保障措施以及商业和财务结构。<sup>[3](https://www.ifc.org/en/pressroom/2022/ifc-and-mphanda-nkuwa-implementation-office-sign-agreement-to-support-the-development-of-a-1500-mw-hydropower-project-in-mozambique)</sup>

## 财团与特许权

2023年12月13日，莫桑比克政府选定由EDF（40%）、道达尔能源（30%）和住友商事（30%）组成的财团为战略合作伙伴。该财团与莫桑比克电力公司、卡布拉巴萨水电公司共同行动，与矿产资源与能源部签署了联合开发协议和框架协议，为未来的特许协议铺平道路；莫桑比克电力公司和卡布拉巴萨水电公司将持有项目30%的股份，财团持有70%。<sup>[1](https://www.edf.fr/en/the-edf-group/dedicated-sections/journalists/all-press-releases/the-consortium-of-edf-totalenergies-sumitomo-corporation-entered-into-joint-development-agreement-with-the-government-of-mozambique-for-the-1500-mw-mphanda-nkuwa-hydropower-project)</sup> 莫桑比克部长会议随后批准将特许权授予姆潘达恩库瓦水电公司，涵盖电站的设计、建设、所有权、运营、维护、融资、保险和管理；部长会议授权矿产资源与能源部长签署特许合同。<sup>[7](https://portaldogoverno.gov.mz/governo-concessiona-empreendimento-hidroelectrico-de-mphanda-nkuwa/)</sup>

**融资与成本。** 已公布的成本数据因范围和日期而异。国际金融公司2022年描述项目估算造价为45亿美元。<sup>[3](https://www.ifc.org/en/pressroom/2022/ifc-and-mphanda-nkuwa-implementation-office-sign-agreement-to-support-the-development-of-a-1500-mw-hydropower-project-in-mozambique)</sup> 世界银行行长阿贾伊·班加估算为50亿至60亿美元，并表示最终成本尚待确定。<sup>[4](https://apnews.com/article/2c661562fb5de1dcaaa5d3681ac86c54)</sup> 商业与人权资源中心援引的2025年风险评估将总额定为64亿美元，其中50亿美元用于大坝和发电厂，14亿美元用于输电线路。<sup>[5](https://www.bhrrc.org/en/latest-news/mozambique-the-mphanda-nkuwa-dam-project-allegedly-poses-severe-human-rights-risks-incl-company-responses/)</sup> 世界银行并非直接为项目融资，而是为法律、环境和输电工作提供优惠资金、部分风险担保和政治风险保险。[非洲开发银行](https://www.edgepedia.org/zh/african-development-bank)计划为一条区域输电线路筹集优惠资金和赠款，以便向工业中心供电并实现电力出口。<sup>[4](https://apnews.com/article/2c661562fb5de1dcaaa5d3681ac86c54)</sup><sup> • </sup><sup>[10](https://www.afdb.org/en/news-and-events/press-releases/mozambique-advances-mphanda-nkuwa-hydropower-project-african-development-bank-support-90816)</sup>

## 市场与目的

该项目旨在帮助莫桑比克到2030年实现全民用电，促进工业化，并使该国成为区域能源枢纽，将剩余电力出口到包括南非在内的邻国，那里对清洁能源的需求很高。<sup>[3](https://www.ifc.org/en/pressroom/2022/ifc-and-mphanda-nkuwa-implementation-office-sign-agreement-to-support-the-development-of-a-1500-mw-hydropower-project-in-mozambique)</sup> 据EDF称，该项目将使莫桑比克的发电能力提高50%以上，为该国及周边地区超过300万户家庭供电。<sup>[1](https://www.edf.fr/en/the-edf-group/dedicated-sections/journalists/all-press-releases/the-consortium-of-edf-totalenergies-sumitomo-corporation-entered-into-joint-development-agreement-with-the-government-of-mozambique-for-the-1500-mw-mphanda-nkuwa-hydropower-project)</sup> 电站预计于2031年开始运营，帮助一个面临10，000兆瓦电力缺口的地区。<sup>[4](https://apnews.com/article/2c661562fb5de1dcaaa5d3681ac86c54)</sup> 相比之下，政府门户网站预计商业运营将于2032年开始。<sup>[7](https://portaldogoverno.gov.mz/governo-concessiona-empreendimento-hidroelectrico-de-mphanda-nkuwa/)</sup>

## 环境与社会关切

民间社会组织持续提出反对意见。2024年10月，莫桑比克环境正义组织（“地球之友”莫桑比克分会）、日本“地球之友”和CCFD-Terre Solidaire向住友商事发出质询，指出坝址附近存在地震活动风险、对土地和生物多样性的累积影响以及社区生计丧失等问题。<sup>[11](https://foejapan.org/en/issue/20241030/21046/)</sup> CCFD-Terre Solidaire和环境正义组织2025年发布的一份报告基于245人以上的证词，称项目周边存在恐惧和压制气氛，包括恐吓、威胁和任意逮捕，并指出2023年12月的合作协议是在任何社区协商会议召开之前签署的。<sup>[12](https://ccfd-terresolidaire.org/edf-et-totalenergies-une-transition-verte-sur-le-dos-des-populations-au-mozambique/)</sup><sup> • </sup><sup>[6](https://ja4change.org/wp-content/uploads/2025/02/jas-summary-of-mnk-concerns_february-2025-1.pdf)</sup>

预计搬迁规模很大。商业与人权资源中心记录，项目使1，400多个家庭、至少8，120人面临被迫搬迁的威胁，下游赞比西三角洲约35万人可能因洪泛平原农业丧失而面临粮食不安全；欧洲宪法与人权中心发布的报告指出，超过100平方公里的土地将被淹没，文化遗址和圣地面临被淹没的风险。<sup>[5](https://www.bhrrc.org/en/latest-news/mozambique-the-mphanda-nkuwa-dam-project-allegedly-poses-severe-human-rights-risks-incl-company-responses/)</sup><sup> • </sup><sup>[13](https://www.ecchr.eu/en/publication/without-our-land-and-river-we-will-starve/)</sup> 针对这些指控，EDF、道达尔能源和住友商事财团表示，明确谴责针对社区、社区代表或人权维护者的任何形式的暴力、恐吓、任意拘留或报复行为。<sup>[5](https://www.bhrrc.org/en/latest-news/mozambique-the-mphanda-nkuwa-dam-project-allegedly-poses-severe-human-rights-risks-incl-company-responses/)</sup>

在水文方面，2011年的环境流量研究发现，提供满槽流量的释放最多只会使姆潘达恩库瓦的年发电量下降2%，而环境流量释放对近海捕虾渔业的单独经济收益，可能超过环境流量释放给卡布拉巴萨和姆潘达恩库瓦两座电站造成的发电损失总成本。<sup>[8](https://www.researchgate.net/publication/313726306_Implications_of_Mpanda_Nkuwa_Hydropower_Project_for_Environmental_Flow_Releases_in_the_Lower_Zambezi_Valley)</sup>

## References

1. [EDF press release, 13 December 2023: EDF–TotalEnergies–Sumitomo consortium joint development agreement for the 1,500 MW Mphanda Nkuwa hydropower project](https://www.edf.fr/en/the-edf-group/dedicated-sections/journalists/all-press-releases/the-consortium-of-edf-totalenergies-sumitomo-corporation-entered-into-joint-development-agreement-with-the-government-of-mozambique-for-the-1500-mw-mphanda-nkuwa-hydropower-project)
2. [SADC Investment Portal: Mozambique – Mphanda Nkuwa Hydropower Project 1,500 MW (HNMK)](https://invest.sadc.int/opportunities/project-details/view_express_entity/32)
3. [IFC and Mphanda Nkuwa Implementation Office sign agreement to support the development of a 1,500 MW hydropower project in Mozambique, 18 May 2022](https://www.ifc.org/en/pressroom/2022/ifc-and-mphanda-nkuwa-implementation-office-sign-agreement-to-support-the-development-of-a-1500-mw-hydropower-project-in-mozambique)
4. [AP News: Mozambique embraces a $6 billion electricity project, southern Africa's biggest in 50 years](https://apnews.com/article/2c661562fb5de1dcaaa5d3681ac86c54)
5. [Business and Human Rights Centre: Mozambique – the Mphanda Nkuwa dam project allegedly poses severe human rights risks; incl. company responses](https://www.bhrrc.org/en/latest-news/mozambique-the-mphanda-nkuwa-dam-project-allegedly-poses-severe-human-rights-risks-incl-company-responses/)
6. [Justiça Ambiental: Summary of concerns around the Mphanda Nkuwa hydroelectric dam project, February 2025](https://ja4change.org/wp-content/uploads/2025/02/jas-summary-of-mnk-concerns_february-2025-1.pdf)
7. [Portal do Governo de Moçambique: Governo concessiona empreendimento hidroeléctrico de Mphanda-Nkuwa](https://portaldogoverno.gov.mz/governo-concessiona-empreendimento-hidroelectrico-de-mphanda-nkuwa/)
8. [Beilfuss & Douthwaite: Implications of Mpanda Nkuwa Hydropower Project for Environmental Flow Releases in the Lower Zambezi Valley (2011)](https://www.researchgate.net/publication/313726306_Implications_of_Mpanda_Nkuwa_Hydropower_Project_for_Environmental_Flow_Releases_in_the_Lower_Zambezi_Valley)
9. [Joseph Hanlon, Club of Mozambique: Mphanda Nkuwa & hydrogen; special report](https://clubofmozambique.com/news/mozambique-mphanda-nkuwa-special-report-by-joseph-hanlon/)
10. [African Development Bank: Mozambique advances Mphanda Nkuwa Hydropower Project with African Development Bank support](https://www.afdb.org/en/news-and-events/press-releases/mozambique-advances-mphanda-nkuwa-hydropower-project-african-development-bank-support-90816)
11. [Friends of the Earth Japan: Inquiry letter sent to Sumitomo Corp. on their involvement in the mega dam project in Mozambique, 30 October 2024](https://foejapan.org/en/issue/20241030/21046/)
12. [CCFD-Terre Solidaire: EDF et TotalEnergies, une transition verte sur le dos des populations au Mozambique?](https://ccfd-terresolidaire.org/edf-et-totalenergies-une-transition-verte-sur-le-dos-des-populations-au-mozambique/)
13. [ECCHR: "Without our land and river, we will starve" – Uncovering green colonialism in the EDF, Sumitomo and TotalEnergies hydroelectric dam project in Mozambique (2025)](https://www.ecchr.eu/en/publication/without-our-land-and-river-we-will-starve/)

---
*Initially written Oct 15, 2026*

Topic: 技术与人造世界 › 能源技术 › 水力发电 › African hydroelectric plants and projects

Copyright 2026 Edgepedia

License: Edgepedia Community License 1.0, https://www.edgepedia.org/edgepedia/license

Source: https://www.edgepedia.org/zh/mphanda-nkuwa-project

English original: https://www.edgepedia.org/mphanda-nkuwa-project